Description

When (if ever) thorough review becomes an option, the patch will probably need to be split in multiple parts. This will have to be done using a MQ Queue, preferably in a way that the game compiles and runs at any point in the sequence.

History

#1 Updated by Hirundo over 10 years ago

  • Priority changed from Normal to Low

#2 Updated by Hirundo over 10 years ago

  • Target version changed from trunk-ready to IS2.2

This will probably be done using branches. Branch structure should be done for 2.2

#3 Updated by Hirundo about 10 years ago

  • Target version changed from IS2.2 to IS2.3
  • % Done changed from 0 to 50

The first part of IS is already split. The rest can / will be done later, but it takes a lot of work.